CMJ Daily Tape
OFFTAKE | ANTIMONY
Larvotto Resources announced on 18 November that its two concentrate offtake partners, Glencore (gold concentrate) and Wogen Resources (antimony concentrate), have each provided US$15 million in prepayments, a combined US$30 million, for future concentrate from the Hillgrove gold-antimony project in New South Wales, Australia. All funds have been received. The prepayments are on usual commercial terms, are settled through concentrate deliveries and are available for 12 months. Antimony concentrate shipments to Wogen began in October and gold concentrate deliveries to Glencore have now started. Larvotto said disruptions tied to the war in the Strait of Hormuz delayed critical items, including dry tailings filter presses, and it expects to finalise commissioning by end-December 2026, with first gold doré in late November.
US$30 million for a four-month commissioning phase, repaid in concentrate, means the offtakers are now financing the ramp-up, not only buying the output. The 12-month window is the number to watch: each week lost to late filter presses or slow recoveries pushes deliveries against a fixed settlement clock. Wogen carries the antimony delivery risk and Glencore the gold. If commissioning slips past December, the next conversation with both offtakers is about delivery schedules, not price.
FUNDING | TUNGSTEN
Natural Resources Canada said on 16 November it will invest up to C$14 million in Fireweed Metals to fund engineering, validation and technical work on the Mactung tungsten project in the Selwyn Mountains, Yukon, as it moves toward a final investment decision. The release gives no FID date and no tonnage or grade figures. It follows up to C$12.9 million granted in 2024 through the Critical Minerals Infrastructure Fund for North Canol Road and transmission studies. Fireweed CEO Ian Gibbs said the team is driving toward an FID.
C$14 million buys engineering, not concentrate. With the C$12.9 million from 2024 for road and power studies, Canada has now committed up to C$26.9 million to Mactung without a construction decision or a published FID date. The binding constraint is access: a deposit in the Selwyn Mountains needs the North Canol Road and grid work before any tungsten concentrate reaches a North American converter. Buyers qualifying non-Chinese APT feed should treat this as study funding, not a supply date.
PREPAYMENT | COPPER | ZINC
Orion Minerals announced on 20 November it has received the first drawdown of US$6.7 million from Glencore (yes, Glencore again!) under the prepayment agreement for the Prieska Copper Zinc Mine in South Africa's Northern Cape. The funds come from the US$40 million Tranche A facility, which became unconditional on 19 October, and pay for early construction at the Uppers Mine before the December break. Full construction is scheduled to start in January 2027, with first concentrate targeted by end-2027, according to the company.
US$6.7 million is about 17% of Tranche A, released to pay for site works in the weeks before South Africa's December shutdown. The schedule leaves roughly twelve months between full construction in January 2027 and first concentrate by end-2027, a tight window for a mine restart. Glencore holds both the funding and the offtake, so any slip in construction moves repayment and concentrate delivery timing together. Contractor awards in December are the first test.
LEADERSHIP | RARE EARTHS
Lynas Rare Earths will hold its annual general meeting in Sydney on 25 November without a permanent chief executive, Reuters reported. Chairman John Humphrey had said last month he expected to name a new CEO before the meeting; he has since confirmed that a highly credentialed candidate withdrew for personal reasons before a full-board interview. Former CEO Amanda Lacaze announced her retirement in January after 12 years. Pol Le Roux, formerly chief operating officer, has been interim CEO since the end of June.
The vacancy matters more to the order book than to the share register. Reuters describes Lynas as the only commercial producer of both light and heavy rare earths outside China, and the company is carrying its Towards 2030 plan plus the October Brazil mine acquisition. Magnet makers qualifying separated heavy rare earth oxide want a counterparty that can sign multi-year volume commitments. An interim chief can run the plants; long-term offtake and capex decisions on Brazil tend to wait for a permanent one.
LOCAL CONTENT | LITHIUM
Zimbabwe will require miners, government entities and other large businesses to source at least 15% of their inputs from local manufacturers, Finance Minister Mthuli Ncube said in his budget speech on 19 November, Reuters reported. Ncube also said export tax on lithium concentrate will be calculated on the value of the lithium sulphate it could produce, converting 6% concentrate at five tonnes to one tonne of sulphate, with sulphate exports untaxed. He did not say whether the January 2027 ban on concentrate exports will take effect as scheduled.
The 15% rule applies to what a lithium miner buys, not what it sells: reagents, mill liners, explosives, spares. The industry projection Reuters cites puts 2027 output at 2.3 million tonnes of concentrate and 208,000 tonnes of sulphate. At the 5:1 tax ratio, that sulphate absorbs about 1.04 million tonnes of concentrate, under half of output. Without a confirmed ban date, most tonnes still leave as concentrate taxed on sulphate value, under a procurement rule with no published basis or penalty.